OVERVIEW ON AN OPEN PIT MINE PLANNING OF THE PICKSTONE PEERLESS IN A VOLATILE ENVIRONMENT

Authors

  • Tapiwa Frank Kwachara Ngoroyemoto Manicaland State University of Applied Sciences
  • Charles Chewu Manicaland State University of Applied Sciences
  • Desire Runganga Manicaland State University of Applied Sciences
  • Tatenda Nyamagudza Manicaland State University of Applied Sciences
  • Ashley Ruvimbo Sabao Manicaland State University of Applied Sciences

DOI:

https://doi.org/10.30556/imj.Vol25.No1.2022.1288

Keywords:

availability, environment, mining, scheduling, volatile

Abstract

The prevailing mining climate is highly characterized by unstable consumables pricing systems, a volatile economy and skyrocketing operational costs, and exacerbated by a steady decline and intermittence in the availability of electricity. Zimbabwean mines need to extensively capitalize on the opportunity to improve productivity by emphasizing variables they can control, predominantly operational efficiency to avoid resizing of operations or facilitating downsizing by relatively insignificant factors. In this study, cycle times, rig penetration, utilization, availability and payloads were used to evaluate the mining cycles, operator costs and the information was compared against the life of mine plans with block models. Shifts were restructured to be concordant to the schedule provided by the utility company to save fuel that was being used to power metallurgical plant. Several challenges have been identified as the principal reasons behind discrepancies between the theoretical capabilities of equipment were proven to be achievable by a trial schedule which reduced the 7 days/month to less than 2 days a month. The new schedule reflects a theoretical improvement of close to 25% and significantly lower operational costs. The current mining fleet is capable of meeting the stipulated targets and even achieving more even within tough working environments characterized by harsh load shedding schedules and volatile inflation rates; however, this requires stringent monitoring and evaluation of unit process. By adopting the recommended short term production plans will avoid resizing of operations as it automatically reduces the operational costs by US $3 million annually whilst coercing both operators and management to improve their operational efficiency.

Author Biographies

Tapiwa Frank Kwachara Ngoroyemoto, Manicaland State University of Applied Sciences

Mining and Mineral Processing Engineering

Head of Department

Charles Chewu, Manicaland State University of Applied Sciences

Lecturer

Desire Runganga, Manicaland State University of Applied Sciences

Lecturer

Tatenda Nyamagudza, Manicaland State University of Applied Sciences

Lecturer

Ashley Ruvimbo Sabao, Manicaland State University of Applied Sciences

Lectuerer

References

Business and Human Rights Resource Centre (2020) Zimbabwe: Chamber of mines says power cuts putting mine workers’ lives at risk, www.business-humanrights.org. Available at: https://www.business-humanrights.org/en/latest-news/zimbabwe-chamber-of-mines-says-power-cuts-putting-mine-workers-lives-at-risk/ (Accessed: 15 December 2021).

Cheng, J. E. (2019) ‘Match factor determination of excavator-truck combination in surface mining: Case study of merit pila coalfield, Sarawak’, Geological Behavior, 3(1), pp. 28–29. doi: 10.26480/gbr.01.2019.28.29.

Dagdelen, K. (2001) ‘Open pit optimization - Strategies for improving economics of mining projects through mine planning’, in 17th International Mining Congress and Exhibition of Turkey. Ankara: IMCET2001, pp. 117–121.

Darling, P. (2011) SME mining engineering handbook. 3rd edn. Society for Mining, Metallurgy, and Exploration.

Kaseke, N. (2013) ‘Emergence of electricity crisis in Zimbabwe, Reform response and cost implications’, Journal of Business Management & Social Sciences Research, 2(10), pp. 1–16.

Kennedy, B. A. (2009) Surface mining. 2nd edn. Littleton: Society for Mining Metallurgy and Exploration Inc.

Lowrie, R. L. (2009) SME mining reference handbook. Littleton: Society for Mining Metallurgy and Exploration Inc.

Mahonye, N. and Zengeni, T. (2019) ‘Exchange rate impact on output and inflation: A historical perspective from Zimbabwe’, African Journal of Science, Technology, Innovation and Development, 11(3), pp. 347–358. doi: 10.1080/20421338.2019.1575539.

Manyele, S. V. (2017) ‘Investigation of excavator performance factors in an open-pit mine using loading cycle time’, Engineering, 09(07), pp. 599–624. doi: 10.4236/eng.2017.97038.

Mining Zimbabwe (2019) Top ten gold producers in Zimbabwe 2019, miningzimbabwe.com.

Morad, A. M., Pourgol-Mohammad, M. and Sattarvand, J. (2013) ‘Reliability-centered maintenance for off-highway truck: Case study of Sungun copper mine operation equipment’, in Proceedings of the ASME 2013 International Mechanical Engineering Congress & Exposition. San Diego: American Society of Mechanical Engineers, pp. 1–6. doi: 10.1115/IMECE2013-66355.

StartupBiz Zimbabwe (2021) Black market forex exchange rates today 30 June 2021, StartupBiz.co.zw. Available at: https://startupbiz.co.zw/black-market-forex-exchange-rates-today-30-june-2021/ (Accessed: 15 December 2021).

Tomlingson, P. D. (2010) Equipment management workbook: Key to equipment reliability and productivity in mining. Colorado: Society for Mining Metallurgy and Exploration Inc.

ZIMPLATS (2019) 2019 integrated annual report. Guernsey: Zimplats Holding Limited.

Downloads

Published

2022-06-20